WILL RUTH POND AND CONVEYANCE IMPROVEMENTS

WILL RUTH POND AND CONVEYANCE IMPROVEMENTS

Jordan Foster Construction will be the Construction Manager at Risk (CMAR) for the Will Ruth Retention Pond and Conveyance Improvements in Northeast El Paso. For more information, please send Ruben Grajeda, Senior Project Manager for Jordan Foster construction, an email requesting information on the project and bid documents.  He can be reached at: [email protected] 

WR 01 – SWPPP & Temp Perimeter Fencing (CSP)
WR 02 – Environmental Study and Abatement (RFQ)
WR 03 – Traffic Control Plan and Implementation (RFQ)
WR 04 – Demolition (RFQ)
WR 05 – Excavation and Haul Out (CSP)
WR 06 – Concrete Pond Liner (CSP)
WR 07 – Storm and Sanitary Sewer Utility Installation (on Will Ruth and Threadgill) (CSP) 
WR 08 – Rock and Decorative Perimeter Wall (RFQ) 

  • Pre-Advertisement Date: May 1, 2024
  • Pre-Bid Meeting: May 8, 2024
  • Site Visit: May 8, 2024
  • Advertisement Date: May 15, 2024
  • Deadline for Questions: May 22, 2024
  • Questions Clarifications: May 29, 2024
  • Bid Due Date: June 12, 2024
  • Anticipated Award and NTP: Sept. 11, 2024
  • Anticipated Mobilization: Oct. 9, 2024
  • Substantial Completion: April 16, 2026
  • Final Completion: May 16, 2026 