Asset Management Program
Advertised on: September 19, 2023
RFQ SCHEDULE
The following Schedule of Events represents El Paso Water’s best estimate of the schedule that will be followed. El Paso Water reserves the right to modify the schedule as required.
El Paso Water issues RFQ - September 19, 2023
Deadline for submission of requests for clarification - October 3, 2023 by 5:00 P.M. (MT)
El Paso Water provides responses/clarifications - October 12, 2023
Deadline for submission of Statements of SOQ - October 31, 2023 @ 3:00 P.M. (MT)
El Paso Water notifies short-listed firms to arrange for interviews by estimated - Nov. 17, 2023
Short-listed firms to coordinate for tour of 1 referenced utility by estimated date - Feb. 23, 2024
El Paso Water notifies selected firm by estimated date - March 14, 2024
Negotiate Contract and Initial Tasks Scope and Fee by estimated date - April 17, 2024
Present to Board for Approval - June 12, 2024